The Act

Key sections of the Act

8 Rights to progress payments

This section guarantees the right of all to make a claim for works carried out at least every month regardless of what may be in the contract.

9 Amount of progress payment

If there are no specific details in the contract to value the amount of the progress payment the value is to be determined based on the value of work carried out or undertaken to be carried out.

10 Valuation of construction work and related goods and services

This section is the key clause in determining how an adjudicator may value the works carried out. There is some devil in the detail here that can become very important in getting the true value of the work underway to be justified in a claim.

11 Due date for payment

Determines the date for payment and interest rates that may apply to outstanding payments

12 Effect of "pay when paid" provisions

No more tying payments or performance to other parties. The only contract that matters is the one that relates to the claim.

13 Payment claims

Details how to make a progress claim under the act, regardless of what the contract may demand.

14 Payment schedules

Requires the other party to respond to a payment claim within 10 days and if the scheduled amount is less than the claimed amount they must supply all reasons.

15 Consequences of not paying claimant where no payment schedule received

If no payment schedule is received the whole amount of the claim becomes due and the claimant can apply for adjudication to recover that amount.

16 Consequences of not paying claimant in accordance with payment schedule

If the amount paid is not as per the scheduled amount the claimant may apply for adjudication to recover the unpaid amount.

17 Adjudication applications

The adjudication is the vehicle that allows the claimant to present the reasons ( and all relevant documentation) that may satisfy the adjudicator they should be paid the amount they claim they are due. This section also details requirements of to achieve a valid adjudication application, so that the process may successfully proceed.

20 Adjudication responses

The respondent gets the opportunity to respond to the application submission. However they are not entitled to bring up any reasons for not paying the claimed amount.

21 Adjudication procedures

This section details the boundaries that the adjudicator may operate within. Note there is now allowance for legal representation should any conferences be called.

22 Adjudicator's determination

The adjudicator is allowed to consider the act, the contract, the payment claim, the payment schedule and all submissions. The adjudicator must determine the value of any construction work where this is in dispute with regard to the progress payment. The adjudicator may correct any accidental slips or omissions, clerical mistakes or defects of form should they become aware of such an occurrences.

23 Respondent required to pay adjudicated amount

The respondent will be required to pay the claimant the adjudicated amount within 5 days of the determination.

24 Consequence of not paying the claimant the adjudicated amount

Should respondent not pay the adjudicated amount, the claimant can suspend work without any consequence and ask for an adjudication certificate from the ANA.

25 Filing of adjudication certificate as judgment debt

The adjudication certificate is the equivalent of a judgement debt issued by any court. The respondent is not entitled to bring any cross claim, raise any defence in relation to the construction contract or most importantly challenge the adjudicator's determination. Should the respondent commence any proceedings they must pay to the court the determined amount until the completion of the proceedings.

34 No contracting out

No construction contract can exclude the operation of any section of the Act, ever.


website design: SkyRocket SkyRocket website design